In this article
The phrase “transportation consulting” looks promising in a bid alert. Then a principal opens the scope. The buyer wants field data the team has analyzed for years but has never collected itself. Should the firm spend three days preparing qualifications?
Pursue a government contracting opportunity when you can document the requested work, name the people who will deliver it, and afford the proposal effort. For a Chicago engineering firm, that decision starts with one service area in the current solicitation and its addenda. The March 2026 Chicago Metropolitan Agency for Planning procurement below is a closed example you can use to practice the decision.

What was the Chicago-area buyer actually seeking?
The Chicago Metropolitan Agency for Planning (CMAP) issued RFQ 341 for Project Consulting Services in February 2026. It sought to prequalify firms across 14 service areas. A place on a qualifications list was the immediate opportunity. The document describes later project authorizations, so a principal deciding how much to spend on a response should keep future assignments separate from the initial selection.
Consider Service Area 13. CMAP described collecting and processing travel activity data, including counts by vehicle type and intersection approach. It specified 15-minute increments over a defined 24-hour period for turning counts. A firm that builds dashboards from data supplied by others should ask who will obtain, check, and deliver the source counts. Those responsibilities are visible in CMAP’s full RFQ, Attachment 1, Service Area 13.
Read the addenda before using any dates or evaluation factors in the original file. CMAP’s March 16 amendment moved the deadline to March 25 at 3 p.m. Central and required respondents to acknowledge the addendum. It also revised a scoring factor for specified service areas. For an active procurement, the proposal lead should record which changes apply to the chosen service area. Read Addendum 1.
Which questions should a principal settle first?
Give one person responsibility for checking the submission instructions, required acknowledgments, due time, and eligibility requirements. Ask the technical lead to read the actual service description and mark the work the firm would perform. If the two readers are working from different document versions, settle that before people start drafting.
Bring the project manager into the decision. Who has run the fieldwork? Who owns quality control when a device fails or a count file is incomplete? Is the person you intend to name available? A subject-matter expert who has read about a method and a lead who has delivered it provide different evidence. If you expect a partner to do part of the work, verify the solicitation’s teaming instructions and the partner’s role before including them.
How does a bid/no-bid decision matrix work?
This is a fictional principal’s internal scoring exercise for Service Area 13. Give each item two points for verified evidence, one for a gap with a realistic way to close it, and zero for a missing essential element. CMAP publishes its own evaluation factors. The team uses this separate score to decide whether to invest proposal hours.
| Question | Evidence on the table | Score |
|---|---|---|
| Do our operations fit? | The team has processed counts and checked interval files. Its field equipment arrangement still needs confirmation. | 1 / 2 |
| Can we name the delivery team? | An available field lead and a quality reviewer confirm their responsibilities. | 2 / 2 |
| Do our projects prove comparable work? | The referenced assignments used counts collected by another firm. Neither demonstrates capture under this team’s direction. | 0 / 2 |
| Can we afford the response? | The lead estimates 24 staff hours. Sixteen are available before other client deadlines. | 1 / 2 |
The result is four out of eight. This principal’s rule is to pursue at six or above, with a verified example for the essential fieldwork. The firm falls short on both counts. A recognizable buyer name adds nothing to the score.
When is declining the bid the better decision?
Decline when a firm cannot close an essential gap before the decision deadline, or when winning would commit people or equipment it cannot supply. In this example, a polished description of the analytics team would do little to establish field capture experience. The principal could instead approve a bounded effort to find a future teaming opportunity where that team’s analysis is a good fit.
Put the reason in writing. A short record might read, “Decline Service Area 13 as prime. Our sample projects demonstrate analysis. We lack a verified capture example and eight response hours. Revisit when the field lead can cite a comparable assignment.” That note gives business development a concrete reason to revisit the decision when a new solicitation appears.
What should you keep for the next opportunity?
Save the scope excerpt, version and addendum dates, score, decision owner, and evidence that would change a future decision. For opportunities you pursue, record actual proposal hours and whether the firm advanced. Over several comparable pursuits, the team will see where its initial estimate was consistently too low.
Keep reusable proof in a one-page engineering capability statement, then tailor the evidence to each buyer’s instructions. The CMAP procurement page lists current opportunities. AVP’s Chicago marketing work for technical services firms connects qualified opportunities with the principal who owns the proposal decision. Use the growth planner to scope a pursuit review and the project evidence it needs.